Q&A Subject: Markusnet
man-overboard (MOB) matters
Question
no. 0003 |
| Q:
Why is the Markusnet designed to day only to lift one person at a
time? A:
The Markusnet was originally designed as flat square formed net structure to lift
many men from water at the same time. This was in 1980, before the man-overboard matter
became a subject in national and international regulations. As there are now many crane
lifting solutions on the marine market, but no other manual lifting solution and as
experience in our trials have shown, the maximum load one can expect one man to lift is 50
kg, two men 110 kg and that 6 men can hardly lift two men at a time, even with one line
each, we desided to limit the size of the net to one person. |
| |

|